JRH Construction
Commercial Roofing10 min readUpdated April 2026

The $2B Red Oak Data Center Boom: What DataBank April 2026 Financing Means for South DFW Commercial Roofing

By Landry Haight, Commercial Roofing Specialist

DataBank closed $2.0 billion in construction financing on April 21, 2026 to build the first three of eight data centers on a 300-acre Red Oak campus in Ellis County, Texas. DFW9, DFW10, and DFW11 will deliver 600,000 sq ft and 180 MW of capacity, all fully pre-leased. MUFG Bank served as administrative agent. South DFW just became the fastest-growing hyperscale commercial roofing market in North America.

Why is Red Oak the new DFW data center corridor?

Red Oak sits 20 miles south of downtown Dallas in northern Ellis County. The factors that made it inevitable: power availability from the ERCOT southern grid, rail-adjacent fiber backhaul through the BNSF corridor, flat terrain, property tax abatements from Ellis County, and land costs 60-70 percent below north DFW alternatives. DFW is the #2 global data center market behind Northern Virginia with 1,083 MW under construction and 3,870 MW in the development pipeline.

What does hyperscale data center construction mean for commercial roofing?

A 200,000 sq ft hyperscale shell needs 200,000 sq ft of roof. At DFW commercial replacement pricing of $8-15/sqft for TPO on a new-construction tier, that is $1.6M-$3M per facility just for the roofing scope. Across 3 facilities: $5M-$9M on phase one alone. Across all 8: $13M-$24M at the DataBank campus by itself.

What roofing specifications do DFW hyperscale data centers require?

1. Membrane: TPO or PVC, minimum 80-mil, reinforced seams. TPO is the 2026 default for heat-reflectivity and Class A fire rating.

2. Class 4 impact resistance on every roof assembly. Insurance underwriters price hyperscale policies with mandatory Class 4 requirements.

3. High-HVAC-load detailing. Factory-fabricated curb flashings, prefab penetration boots, QA seam welds.

4. Phased installation for Tier III and IV operational continuity.

5. EMR and safety compliance at GC standards. OSHA 30, EMR below 0.85, documented site-specific safety plans.

6. Surety bonding sized to the work. $5M+ bonding to be credible at the bid table.

JRH Construction position on DFW hyperscale

GAF Master Elite (top 2 percent of U.S. GAF contractors). Owens Corning Platinum Preferred. BBB A+. SAM.gov federal contractor registration. $10M+ bonding capacity. 600+ projects since 2019 under founder Joel Hasin. Headquarters at 1767 Old State Highway 24 Suite 210 in Little Elm puts field crews within a 45-minute drive of the Red Oak campus.

South DFW hyperscale timeline

DataBank Phase 1 (DFW9, 10, 11) targets Q3 2026 completion on the first facility, with DFW10 and DFW11 following in Q4 2026 through Q1 2027 - an 18-month acceleration versus pre-financing timeline. Parallel projects in the corridor: Stack Infrastructure Ennis, Aligned Plano-Red-Oak corridor expansion, Digital Realty DFW12. Contractors bidding now book 2026-2027 revenue at volumes that exceed most DFW commercial roofers entire annual book.

Sources

Frequently Asked Questions

How many total data centers are planned at the DataBank Red Oak campus?+
Eight. Phase 1 (DFW9, 10, 11) is funded by the April 21, 2026 $2 billion loan and fully pre-leased. The remaining five are on the 300-acre master plan and will be financed in subsequent phases.
What is the total megawatt capacity at full buildout?+
Phase 1 alone delivers 180 MW across 600,000 sq ft. Extrapolated to all 8 facilities at similar scale, the campus will exceed 480 MW at full buildout, making it one of the largest single-operator campuses in Texas.
When does Phase 1 construction finish?+
DFW9 is targeting Q3 2026 for first power. DFW10 follows by late Q4 2026. DFW11 completes the phase by Q1 2027.
Is this the largest construction financing for a DFW data center to date?+
It is the largest in DataBank corporate history. Across the DFW market, larger aggregate deals exist (Meta, Digital Realty, Compass), but DataBank $2B in a single construction facility for three buildings is a benchmark single-transaction data point.
What is the commercial roofing square footage opportunity across all 8 campus buildings?+
Estimated 1.6 million square feet of roof area at full buildout. At mid-range 2026 TPO pricing ($10/sqft average for hyperscale spec with Class 4 impact resistance), the campus-wide roofing scope approaches $16 million across the project lifecycle.

Request a Hyperscale Capabilities Packet

GAF Master Elite. $10M+ bonding. SAM.gov. 600+ projects. 45-min from Red Oak.

Call (469) 888-6903
Services

Our Roofing Services

From storm damage repair to luxury estate roofing, we deliver premium results across every project type in Dallas-Fort Worth.